One of Norway’s largest climate initiatives involves Hafslund establishing a CO2 terminal at the Port of Oslo.

South Harbour

Hafslund is building a carbon capture facility at the waste incineration plant at Klemetsrud. CO2 from the flue gas produced during waste incineration will be liquefied before being transported to temporary storage at the Port of Oslo and then onwards to permanent storage. As part of this project, a CO2 terminal will be established at Kneppeskjær in the Port of Oslo.

Such a terminal includes receiving facilities for tanker trucks, intermediate storage tanks with the necessary associated piping and technical equipment, loading facilities for CO2 ships, and pipelines connecting the intermediate storage tanks to the loading facilities.

The receiving facility, intermediate storage tanks and technical support equipment will be located at the inner end of Sjursøya, while the ship-loading facilities will be situated on the eastern side of the Kneppeskjær pier. Northern Lights will call at the port approximately every four days and spend around one day loading before sailing to their terminal off Øygarden in Western Norway for permanent CO2 storage. 

Three storage tanks will be built, each approximately 42 metres high and 10.5 metres wide.

Noise calculations have been carried out for the construction phase to ensure that the project complies with applicable limits on noise affecting the surrounding area.

Sjursøya with the three storage tanks
Sjursøya with the three storage tanks.

Project timeline

Phasing plan for the development of Sydhavna

Phasing plan

Scroll to the right to see all the information in the table:

Start month​ End month​ ActivityLocation/PhaseComment
​April 2026 ​February 2027 Excavation, piling and foundation work Phase 1 The project has opted for drilled steel core piles, in part to reduce the impact on the surrounding area (noise and vibrations).
​August 2026 October 2026​ Excavation, pipe laying​  Phase 2  Construction of a culvert and buried pipeline
​October 2026 November 2026​ Installation of CO2 pipes under the quay​  Phase 3  Installation of pipes before the quay deck at Kneppeskjær is closed up again.
March 2027May 2028Groundworks, installation and lifting of CO2 tanks, technical installations Phases 1 and 4 Once the CO2 tanks have been lifted into place, work on the remaining technical installations begins.
​March 2027 August 2027​ Technical installations for unloading tanker trucks Phase 5 Conversion on existing foundation from fuel unloading to CO2 reception.
​July 2027 September 2027​ Excavation, pipe laying​  Phase 6 Excavate a trench, lay CO2 pipes and electrical conduits, then backfill the trench.
​September 2027 November 2027​ Excavation, pipe laying​  Phase 7 Excavating a trench, laying CO2 pipes and electrical conduits, then backfilling the trench.
​November 2027 January 2028​ Excavation, pipe laying​  Phase 8 Excavating a trench, laying CO2 pipes and electrical conduits, then backfilling the trench.
​January 2028 May 2028​ Excavation, pipe laying​  Phase 9 Excavating a trench, laying CO2 pipes and electrical conduits, then backfilling the trench.
January 2028 February 2028 Installation of loading arm for ship loading Phase 10 Installation of technical infrastructure for unloading vessels.

Background

At Hafslund’s waste-to-energy plant at Klemetsrud, we incinerate residual waste and use the heat to generate electricity and district heating. Although the flue gas from the incineration process is now cleaned very effectively, it still contains CO2.

Removing CO2 from emissions from the incineration process will reduce Oslo’s total emissions by nearly 20 per cent. This measure is crucial for the City of Oslo to achieve its target of reducing greenhouse gas emissions by 95 per cent by 2030 – a target set out in the municipal master plan and adopted in the Climate Strategy for Oslo towards 2030.

At the new carbon capture facility, CO2 is captured from the flue gas produced by waste incineration and converted into liquid form. The liquid CO2 is then transported to the CO2 terminal at the Port of Oslo before being shipped for permanent storage.

The facility is scheduled for completion and commissioning in 2029.

Consent for construction of the Sydhavna CO2 terminal

Hafslund Celsio AS has applied to the Norwegian Directorate for Civil Protection (DSB) for consent to build the Sydhavna CO2 terminal on Sjursøya.
Construction of a CO2 terminal on Sjursøya in the City of Oslo

On 10.02.2026, the Norwegian Directorate for Civil Protection (DSB) granted Hafslund Celsio AS consent to construct the Sydhavna CO2 terminal.

Noise

Hafslund is in dialogue with Nordstrand borough about the construction work at the Port of Oslo. Representatives from the borough’s Chief Medical Officer’s office have visited the site and been briefed on the project.

The consultancy SWECO has calculated the expected noise levels from the construction work.

Information for neighbours

Hafslund held an information meeting for neighbours about the project on Thursday, 9 April 2026. Click here to view the presentation from the meeting.

Future neighbourhood meetings will be announced on this website and in Nordstrands blad.

Please get in touch if you have any questions

  1. Truls E. A. Jemtland

    Truls E. A. Jemtland

    Communication Manager Hafslund Celsio

This site is using cookies from Matomo for statistics and for tracking user behavior on the site. Read more about how we are using cookies here