Elgsjøvegen – a construction road reclaimed by nature
How do you build a road through fragile high-mountain terrain—and ensure that nature recovers? Elgsjøvegen on Dovrefjell shows that it is possible.
Using innovative, nature-based solutions, an essential construction access road was built, used – and then restored to its natural state, with documented regrowth of native mountain vegetation.
Not all construction access roads can be built this way. Nevertheless, Hafslund hopes the project can inspire others looking to minimise their impact on nature and serve as an example of what can be done when traditional road construction is not an option.
Challenge
- Elgsjø Dam required rehabilitation to meet current dam safety requirements.
- To transport machinery and construction materials to the site, it was necessary to build an approximately 2 km access road from Bekkelægret to the dam.
- The entire route lies within Knutshø Protected Landscape Area, in wild reindeer habitat and in fragile high-mountain terrain at around 1,100 metres above sea level.
- The authorities therefore imposed strict requirements to minimise land use and restore and revegetate the site once construction was complete.
Measures
- A temporary construction access road with a permanent base course was built with minimal disturbance to the terrain, keeping the road surface low so that it would resemble a vehicle track after restoration.
- Topsoil (soil and vegetation) containing a natural seed bank was stripped off before construction, temporarily stored on geotextile fabric and put back afterwards.
- Vegetation was reused locally and reinstated in the same vegetation type (bog, exposed ridge or willow heath) as the area from which the material was removed.
- The measures were planned in close collaboration between the developer’s (Hafslund/GLB) technical and environmental specialists and experts from the Norwegian Institute for Nature Research (NINA).
- Vegetation establishment along Elgsjøvegen in Oppdal municipality following a hydropower dam upgrade. Results from monitoring in 2023 - Norwegian Research Information Repository
- Re-establishment of vegetation along Elgsjøvegen, Oppdal municipality, following upgrades to a hydropower dam - Norwegian Research Information Repository
- After construction was completed in 2013, the road was restored so that its base layer is concealed, while remaining strong enough to support vehicles for future inspections and minor maintenance.
- Hydropower is renewable energy, and hydropower facilities require maintenance only at long intervals. If major maintenance is needed again at Elgsjødammen, the roadside ditches can be reopened and a fully functional construction access road temporarily established for the duration of the work. Once the work is completed, the road can be restored to a vehicle track.
Had no approach to road construction and dam rehabilitation been found that was both economically viable and met the environmental authorities’ requirements for a construction permit under the conservation regulations, permanently discontinuing the regulation of water levels would have been a likely alternative. In this light, the interdisciplinary collaboration between environmental and technical specialists, which shaped the way the road was built, was a key factor in allowing water level regulation to continue.
-
About GLB
Glommen og Lågens brukseierforening (GLB) owns the dam and was the project owner. Hafslund is the largest owner of GLB and currently operates GLB’s facilities.
Image examples
Results of the measures
- Systematic monitoring of vegetation in 2016, 2018 and 2023 shows that nature is recovering.
- In 2023, vegetation cover exceeds 90% in wetlands and willow heath, and is around 70% on exposed ridges, where regrowth naturally takes longer.
- More than 100 plant species have been recorded, and characteristic species are becoming more abundant:
- willows in willow heath
- sedges in bogs and wetlands
- heather species on the ridges
- The results show that the vegetation is gradually becoming more similar to the local undisturbed mountain vegetation, at different rates across the various habitat types.
- The data series from Elgsjøvegen is considered highly valuable, as there is little long-term documentation of the effectiveness of mitigation measures in mountain construction projects. The findings are highly applicable to other projects in sensitive natural environments.
The project received the Damkrona award for 2017. Damkrona is the honorary award of NNCOLD (the Norwegian National Committee on Large Dams), established to promote sound landscape, environmental and technical solutions for infrastructure in regulated watercourses.
Example images (before/after)
Photos taken from the same viewpoints in different years clearly show how the road has changed from a construction access road to an unobtrusive track with a revegetated surface.