Cleaning up after nearly a century of power generation

By removing contaminated concrete pipes from the 1930s at Kroken, we are restoring this walking area to its natural state and ensuring safe access for years to come.

Cleaning up after nearly a century of power generation at Kroken in Lillehammer
Publisert:

Where: The intake area at Mesna power station, by Kroken dam and Birkebeinervegen in Lillehammer municipality.

Challenge

Two parallel concrete pipes have been buried in the ground since the 1930s. They were decommissioned in the 1960s but have remained underground as a barrier.

Black and white image showing railroad tracks parallel to a large, mesh-covered pipe in a forest clearing.
Penstocks
Photos from the 1930s: The images show the pipeline foundation after the formwork was removed (right), and the reinforcement installed before the concrete was poured (left). (Source: Maihaugen digital archive – photographer Marius Berge).

The main challenge was twofold:

  • Environmental pollutants: The pipes have an internal coating of black tar containing PAH compounds (environmental pollutants). This coating meant we could not reuse the concrete as a base for walking trails, as we had originally intended.
  • Safety and barriers: Users of the area have expressed concern about the deteriorating condition of the pipes. In addition, the pipeline has acted as a physical barrier to mechanised forestry operations and disrupted the natural contours of the terrain where it is elevated above the surrounding ground.

Measures

We are currently carrying out a complete remediation of the pipeline route. The work is extensive and is scheduled for completion in May 2026.

Completed and planned measures include:

  • Complete removal: We have excavated and removed 5,200 tonnes of contaminated concrete. Every last piece, including the reinforcing steel and contaminated coating, is transported off-site and delivered to an authorised waste facility.
  • Handling unexpected discoveries: During excavation, we uncovered unexpected building remnants and additional steel pipes, which we are also removing to clear the site completely.
  • Environmentally sensitive construction practices: We avoid clearing woodland during the nesting season (April–July) and have established procedures to prevent the spread of non-native species such as garden lupin via construction machinery.
  • Protecting the water supply: We ensure that excavation work does not damage the existing water main that runs beneath Birkebeinervegen.
Three people in high-visibility safety gear and hard hats stand on a snowy excavation site in front of a forest.
An excavator digging a trench on a muddy construction site with exposed pipes and trees in the background.
Site visit to Kroken: On the left, project manager Rune Haug and Stig Morten Løken explain the work during a visit by Lillehammer Mayor Hans Olav Sundfør and GD journalist Asmund Hanslien in November 2025. The photo on the right shows excavation work along the pipeline route.

– A positive environmental initiative

Project manager Rune Haug stresses the importance of taking action now to address the old installations.

“We believe this is a positive environmental measure, as we are removing old, contaminated concrete that has lain ‘unused’ in the ground since the 1960s. We are also eliminating a potential risk to third parties should the pipeline collapse at some point in the future,” Haug explains.

He also has good news for hikers and skiers in the area:

“The final stage of the clean-up will be completed before 17 May (2026). By then, the floodlit trail over the old pipeline route will have been widened and resurfaced with fresh gravel. The overhead power lines for the lighting have also been buried,” says Haug.

Results of the measures

Once this project is complete, the natural landscape at Kroken will be free of these traces of past human activity.

The results include:

  • Environmental remediation: We have completely removed the environmental pollutants (PAHs) from the cycle and eliminated a potential source of soil contamination.
  • Improved walking and ski trails: Once the pipes have been removed, we will level the route to make it better suited for skiing and walking. The floodlit trail already has new lighting poles and is ready for use.
  • Natural landscape: By using local soil containing native seeds and plant material, we help the original vegetation grow back naturally, without introducing non-native species.
  • Removing barriers: The terrain is smoothed out to improve conditions for forestry operations and give the landscape a more natural appearance.